DESIGNMISSION 015 · Components · Capacitor deratingFoundational

A 10 µF Capacitor That Isn’t 10 µF Here

The as-built 5 V rail uses three C-A capacitors marked 10 µF and resets after hot storage. Design a replacement bank using one, two or three populated positions. Apply the supplied operating factors to both tolerance corners.

Requirements

Rail · 5.0 VOutput contract · 8–18 µF effectiveWorst ambient · 85°CService allowance · 5 yearsPlacement · 12 mm²
  1. 01Qualify the capacitor bank
  2. 02Verify effective capacitance
Circuit and case data
Circuit and case data

Qualification contract

The regulator vendor requires 8–18 µF effective output capacitance throughout the stated operating life. Voltage rating needs 25% headroom. Only 12 mm² is available inside the qualified low-inductance placement region.

The supplier tables below give independent worst-case retention factors at this mission’s 5 V bias, 85°C endpoint and five-year allowance. Multiply them with the negative capacitance tolerance. Do not infer DC-bias behavior from “X5R,” “X7R,” case size or voltage rating alone. The numeric bias, temperature, and aging factors are fictional supplier-qualified operating-envelope multipliers for this exercise. They are applied to both tolerance corners so the bank has a bounded minimum and maximum effective capacitance. Real MLCC qualification requires part-number-specific minimum/maximum characterization versus bias, temperature, frequency, and age.

Supplier characterization packet
Values supplied specifically for this design envelope
CandidateTolerance5 V bias85°C5-yearArea each
C-A · 10 µF / 6.3 V X5R 0603±20%38%85%95%1.3 mm²
C-B · 10 µF / 10 V X7R 0805±10%72%85%97%2.5 mm²
C-C · 22 µF / 10 V X5R 0805±20%46%85%95%2.5 mm²
C-D · 10 µF / 16 V X7R 1206±10%92%85%97%5.1 mm²
C-E · 47 µF / 10 V polymer±20%100%90%100%29.3 mm²

Retention means the fraction remaining after that independent allowance. Candidate E’s polymer dielectric has no supplied DC-bias loss here, but its size and capacitance must still meet the complete contract.

Evidence notebook 0 saved

No evidence saved yet. Measure, inspect the result, then save useful observations.

Current task
Current task

Step 1 of 2

Qualify the output bank

0 evaluated decisions · Draft and verification saved locally
Technical references